The New Medical Pro-Famille Clinique is on the way

Several years back our clinic burned and we found ourselves out on the street. We went on to find a temporary building which is our current location, but now we must move. We received a site to build on , volunteers cleared the lot, an engineer drew our requirements and an architect drew the plans. We are currently building the new clinic as we receive the funds.

blueprint.jpg
haiti art.png

local artist's rendition 

Haiti.jpg
Haiti Progress.jpg
clinic8.jpg
clinic6.jpg
clinic7.jpg
Haitiprogress2.jpg
Clinicprogress5.jpg
clinic9.jpg
UPDATE : July 15, 2022
The foundation is complete!
We were able to complete the initial $60,000 phase for $53,300 and can now move on to building the walls. The walls will take 7,000 cement blocks at $1.50 each.
F1.jpg
F2.jpeg
F3.jpg
F6.jpg
F5.jpg

 UPDATE: October 2022
At the end of October, we were $11,650 into the wall construction. The landlord gave us an ultimatum to move out in November 2022. Our contractor said he could complete enough of the new building in 5 months so that we could move in, the cost is $50,000. The landlord generously agreed to extend the lease until March 31, 2023. 

haiti3.jpg
haiti4.jpg
haiti2.jpg
haiti.jpg

UPDATE: March 1, 2023
Dr. Gerve's new clinic in Cap Haitien is progressing steadily. The walls on the 1st floor have been completed and now the ceiling/ 2nd story floor has been completed. The second floor will be completed down the road as we need more space. Currently we need the 1st floor completed enough to move in by March 31st. To complete the ceiling, plywood is propped in place and held up by poles underneath. Rebar is then laid on top of the plywood.

Pic 1.jpg
Pic 3.jpg

When the rebar layer is completed, the concrete is then hauled up, mixed, and applied.

 

Pic 2.jpg
Pic 4.jpg

That is how the roof went on. We are still on track for the move.

XDXQ0495[1].JPG
EIZA5230[1].JPG
RCOF3778[1].JPG
1b8da4f7-a9ef-401e-9cf1-67548b986085.heic
0901a150-46cb-475d-bece-d2de9e17960a.heic
RCOF3778[1].JPG

                     Update July 6, 2023:
     We Did It... well, not completely but we          finished the new clinic enough so that we           could move in. We have continued to see    patients and serve the community through                                  the transition.

5ccdf05a-bfb4-4436-a3f7-5f39443d4611.heic
3c40edfc-3269-460b-96e8-727c522ba176.heic

April 5, 2024
With the installation of windows and doors this month, the building project will be complete. That isn't to say there aren't more things to do. The solar electrical system upgrade is next on the list.  